2017 CONSTRUCTION PROJECTS

County Road 5 Reconstruction
 
Location:  CR 5 from CR 40 to TH 9 - MAP
Contractor:   R and G Construction Co.
Approx. Start:   May 30, 2017
Approx. Finish:   May 2018
Description:  This project consists of grading, aggregate base and new bridge at Games Lake outlet.
Detour:  MAP
October 5th update:  The contractor is currently installing culverts north of the county park and also working on the grading in that area.  Wet conditions has slowed progress on the north end but construction continues towards TH 9.


2017 Bituminous Surfacing  

Location:  Kandiyohi County - MAP
Contractor:   Duininck, Inc.
Approx. Start:   May 2017
Approx. Finish:   August 2017
Description:  This project consists of new bituminous surfacing and bituminous overlays located throughout Kandiyohi County.
Detour:  There are no detours associated with this project.  Work will be done under traffic.
August 25th update:  Duininck has finished the 2017 contract.


Games Lake County Park Improvements

Location:  Games Lake County Park
Contractor:   Riley Bros. Construction Inc.
Approx. Start:   April 2017
Approx. Finish:   May 2017
Description:  This project consists of new entrance, storm sewer and parking lot construction.
Detour: None.
June 2nd update:  The parking lot project has been completed.


Dovre Township Improvements

Location:  18th St NE and 41st Ave NE, southwest of Sunray gas station
Contractor:  Duininick Inc.
Approx. Start:   May 2017
Approx. Finish:   September 2017
Description:  This project consists of road reconstruction, storm sewer and new box culvert on Hawk Creek.
Detour: None.  Use alternate route
September 8th update:  The project is substantially complete. 



2016 CONSTRUCTION PROJECTS



County Road 5 / TH 23 Bridge Overpass

Location:  Intersection of CR 5 and TH 23, southwest of Willmar
Contractor:   Robert R. Schroeder Construction, Inc. of Glenwood
Approx. Start:   August 1, 2016
Approx. Finish:   June 16, 2017
Description:   Grading, Bituminous Surfacing, Lighting and Bridge No. 34030
Detour Info   MAP
October 5th updateThe project is complete with the exception of the ramp lighting.  Waiting on power to be run to the cabinet.


County Road 40 Reconstruction

Location:  County Road 40 from State Highway 23 to County Road 4 - MAP
Contractor:   Midwest Contracting Inc of Marshall, MN
Approx. Start:   May 2, 2016
Approx. Finish:   September 3, 2016
Description:  This project includes grading and aggregate base
Detour:   Yes - MAP
June 23rd update:  Project is complete.



45th Street SE & CR 23

Location:  45th St SE from CR 23 to TH 12 (1 mile east of Willmar)
Contractor:   Reiner Contracting of Hutchinson, MN
Approx. Start:   July 5, 2016
Approx. Finish:   August 31, 2016
Description:  This project consists of grading, aggregate base, bituminous milling and bituminous surfacing.
Detour:   MAP
June 23rd update:  Project is complete.